»  South Sioux City Substation; Nebraska Public Power District (2019)


»  115 kV Elm Creek Substation Construction Upgrade; Nebraska Public Power District ( 2019)


»  IronCreek Substation: Garland Light & Power Co. (2019)


»  Colfer Substation; United Power (2019)


»  115 - 12.5kV Iron Creek Substation; Tri-State Generation and Transmission Association, Inc. (2019)


»  Nobles 2 Substation; Mortenson Construction (2019)


»  Mead Substation; Western Area Power Administration (2019)


»  34.5kV/345kV, 200 MW Blazing Star 1 Collector Substation; Mortenson Construction (2019)


»  115kV Colfer Substation; Tri-State Generation & Transmission Association, Inc. (2019)


»  A-F Transmission Line; Mortenson Construction (2019) 


»  Blazing Star Below Grade Conduit & Grounding; Mortenson Construction (2019)


»  161 - 345 kV Wizard Substation Electrical Equipment; Omaha Public Power District (2019)


»  NPPD Ainsworth; American Superconductor Corporation (2019)


»  115 kV North Platte Substation; Nebraska Public Power District (2019)


»  115kV East Forks Transmission Line; Mortenson Construction (2019)

 

»  115 kV Monolith Substation; Nebraska Public Power District (2019)


»  Stroud City 1 & 2; Grand River Damn Authority (2019)


»  115 kV Aurora Substation;  Nebraska Public Power District (2019)


»  138/26.4 kV 22.4 MVA Fay Substation; Western Farmers Electric Cooperative (2019)


»  Solomon Forks Transmission Line; Mortenson Construction (2019)

Onsite Video!

 IPC’s transmission line crew pulling 345kV conductor on the Solomon Forks project. 

Watch Video Now!

Drone View

Check out this view of the dirt work taking off at the Colfer Substation!

Colfer Substation

2018

Projects

  

» 345 kV Solomon Forks T-Line; Mortenson Construction (2018)


» Lacey Substation; Western Farmers Electric Cooperative (2018)


» Amber Substation; Western Farmers Electric Cooperative (2018)


» 115kV Emerson Substation; Nebraska Public Power District (2018)  


» Electrical Distribution System and Substation Improvements; City of Norton, KS (2018)


» 69kV Substation 16; North Central Public Power District (2018)


» 230-115x69kV Southeast Substation Autotransformer Addition & Wadsworth Substation Relay Panel Replacement; Lubbock Power and Light (2018)


» 138kV/24.94kV Oryx Pyote Substation; Priority Power Management (2018)


» 138kV/12.47kV Oryx Crane Substation; Priority Power Management (2018)


» 69kV Stakeholder Substation; Lea County Electric Cooperative, Inc. (2018)


» 69kV/24.94kV Columbus Substation; Columbus Electric Cooperative (2018)


» 69kV Roosevelt Substation Construction; Western Farmer's Electric Cooperative (2018)


» 345kV Antelope Substation Modifications; Nebraska Public Power District (2018)


»  115kV Cottonwood Substation Construction; City of Farmington, NM (2017-2018)

2017

Projects Completed

» 230/69kV Paragould and Jonesboro Substations Circuit Switcher Additional Construction; Southwestern Power Administration (2017)


» 69kV West & Power Plant Substation Additions; City of Jackson (2017)


» 500kV Maxwell & Olinda Substations Structure Repairs; Western Area Power Administration (2017)


» 69kV West & Power Plant Substation; City of Jackson (2017)


» 69kV-12.5kV Gibbon Substation Improvements; Nebraska Public Power District (2017)


» 115kV Scottsbluff Substation Modifications; Nebraska Public Power District (2017)


» 115kV Ault Substation Station Service Replacement; Western Area Power Administration (2017)

2016

Projects Completed

» 161kV Gerald Gay Substation; Grand River Dam Authority (2016)


» 69kV Pryor City 3 Substation; Grand River Dam Authority (2016)


» 69kV/12.45kV Aztec Station Construction Project; City of Farmington (2016)


» 69kV City of Aztec Station Revenue Metering Point; City of Farmington (2016)


» 69kV Chicago West Substation; Cornhusker Public Power District (2016)


» 115kV Cheyenne Bus Replacement; Western Area Power Administration (2016)


» 69/12.47kV Aztec Substation; City of Farmington, NM (2016)


» 345/115kV Red Willow Substation & 115/69kV McCook Substation Modifications; Nebraska Public Power District (2016)

2015

Projects Completed

 

» 138kV Breakers and 138/69kV Switches Upgrades; Bryan Texas Utilities (2015)


» Ary Structure Relocate; Nebraska Public Power District (2015)


» 115kV Holyoke Substation; Pony Express Pipeline Phase 2 Tallgrass Energy (2014‐2015)


» 15kV Sterling Deep Rock Terminal; Pony Express Pipeline Phase 2 Tallgrass Energy (2014-2015)